An administrator is using vRealize Operations for capacity modeling to determine how many more ESXi servers are needed to increase time remaining and capacity remaining score. What can be used to…

The correct answer is A. What-If Analysis. https://docs.vmware.com/en/vRealize-Operations/8.10/com.vmware.vcom.core.doc/GUID- 2D2A0CA2-FA40-4D15-AC1B-C2435A63E33A.html

Administering and Operating vRealize Operations

Question

An administrator is using vRealize Operations for capacity modeling to determine how many more ESXi servers are needed to increase time remaining and capacity remaining score. What can be used to accomplish this goal?

Options

  • AWhat-If Analysis
  • BRightsizing
  • COperations Overview
  • DWorkload Optimization

How the community answered

(29 responses)
  • A
    76% (22)
  • B
    7% (2)
  • C
    14% (4)
  • D
    3% (1)

Explanation

https://docs.vmware.com/en/vRealize-Operations/8.10/com.vmware.vcom.core.doc/GUID- 2D2A0CA2-FA40-4D15-AC1B-C2435A63E33A.html