Which of the following is the MOST important component of any change management process?
The correct answer is D. Management approval. See the full explanation below for the reasoning.
Question
Which of the following is the MOST important component of any change management process?
Options
- AScheduling
- BBack-out procedures
- COutage planning
- DManagement approval
How the community answered
(58 responses)- A3% (2)
- B12% (7)
- C5% (3)
- D79% (46)