nerdexam
Cisco

350-601 · Question #649

What occurs during a scheduled electronic programmable logic device (EPLD) update of a Cisco fabric switch supervisor module?

The correct answer is C. The redundant supervisor module takes over for the duration of the update, there is no service. During an EPLD update of a Cisco fabric switch supervisor module, the redundant supervisor module takes over while the update is being performed. This ensures that the system remains operational without disruption. The EPLD update is conducted in such a way that there is…

Network

Question

What occurs during a scheduled electronic programmable logic device (EPLD) update of a Cisco fabric switch supervisor module?

Options

  • AAll traffic through the system is stopped for the duration of the update, and the switch is power
  • BThe redundant supervisor module takes over for the duration of the update, and the switch is
  • CThe redundant supervisor module takes over for the duration of the update, there is no service
  • DAll control plane traffic is stopped for the duration of the update, and the switch remains

How the community answered

(40 responses)
  • A
    8% (3)
  • B
    5% (2)
  • C
    85% (34)
  • D
    3% (1)

Explanation

During an EPLD update of a Cisco fabric switch supervisor module, the redundant supervisor module takes over while the update is being performed. This ensures that the system remains operational without disruption. The EPLD update is conducted in such a way that there is minimal impact on the running services, provided that redundancy is enabled and a secondary supervisor module is present. The redundant supervisor module maintains control of the system, and no service disruption occurs during the update.

Topics

#EPLD upgrade#Supervisor redundancy#High availability#In-service upgrade

Community Discussion

No community discussion yet for this question.

Full 350-601 Practice