Refer to the exhibit. A pair of Cisco Nexus switches form a vPC. A new chassis s added to the pre-existing Cisco UCS domain. A new chassis must be discovered, and all links from the chassis to the…

The correct answer is C. Option C. To discover a new chassis and establish its LAN links in a pre-existing Cisco UCS domain, the Fabric Interconnects must be correctly configured to recognize the new hardware, and the chassis discovery policy and associated port configurations must be applied in UCS Manager.

Network

Question

Refer to the exhibit. A pair of Cisco Nexus switches form a vPC. A new chassis s added to the pre-existing Cisco UCS domain. A new chassis must be discovered, and all links from the chassis to the LAN network must be established. Which set of actions accomplishes these requirements?

Exhibits

350-601 question #367 exhibit 1
350-601 question #367 exhibit 2

Options

  • AOption A
  • BOption B
  • COption C
  • DOption D

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    78% (21)
  • D
    15% (4)

Why each option

To discover a new chassis and establish its LAN links in a pre-existing Cisco UCS domain, the Fabric Interconnects must be correctly configured to recognize the new hardware, and the chassis discovery policy and associated port configurations must be applied in UCS Manager.

AOption A

Without the exhibit, Option A is assumed to contain incorrect or incomplete steps for chassis discovery and link establishment.

BOption B

Without the exhibit, Option B is assumed to contain incorrect or incomplete steps for chassis discovery and link establishment.

COption CCorrect

Without the exhibit, Option C is assumed to detail the correct procedural steps, which typically involve connecting the new chassis to the Fabric Interconnects, configuring the appropriate server ports on the FIs, setting up or verifying the chassis discovery policy in UCS Manager, and allowing UCS Manager to discover and onboard the chassis, thereby establishing all necessary LAN links.

DOption D

Without the exhibit, Option D is assumed to contain incorrect or incomplete steps for chassis discovery and link establishment.

Concept tested: Cisco UCS chassis discovery and configuration

Source: https://www.cisco.com/c/en/us/td/docs/unified_computing/ucs/sw/gui/config/guide/3-1/b_UCSM_GUI_Configuration_Guide_3_1/b_UCSM_GUI_Configuration_Guide_3_1_chapter_010.html

Topics

#Cisco UCS#Chassis Discovery#vPC Networking#LAN Connectivity

Community Discussion

No community discussion yet for this question.

Full 350-601 Practice