Cisco
350-601 · Question #322
Refer to the exhibit. An engineer must schedule the firmware upgrade of the Red1 and Red2 leaf switches. The requirement is to keep the upgrade time to the minimum, avoid any service impact, and…
The correct answer is A. Configure SchedulerPolicy1 for leaf switches Blue1 and Red1, and SchedulerPolicy2 for leaf. We need to define maximum concurrent nodes of 1 to avoid impacting service.
Network
Question
Refer to the exhibit. An engineer must schedule the firmware upgrade of the Red1 and Red2 leaf switches. The requirement is to keep the upgrade time to the minimum, avoid any service impact, and perform the parallel upgrade. Which set of scheduler attributes must be used to meet these requirements?
Exhibit
Options
- AConfigure SchedulerPolicy1 for leaf switches Blue1 and Red1, and SchedulerPolicy2 for leaf
- BConfigure SchedulerPolicy1 for leaf switches Blue1 and Red1, and SchedulerPolicy2 for leaf
- CConfigure SchedulerPolicy1 for all four leaf switches Blue1, Blue2, Red1, and Red2.
- DConfigure SchedulerPolicy1 for all four leaf switches Blue1, Blue2, Red1, and Red2.
How the community answered
(40 responses)- A75% (30)
- B15% (6)
- C8% (3)
- D3% (1)
Explanation
We need to define maximum concurrent nodes of 1 to avoid impacting service.
Topics
#Firmware Upgrade#Cisco ACI#Scheduler Policy#Network Operations