nerdexam
CiscoCisco

350-601 · Question #294

350-601 Question #294: Real Exam Question with Answer & Explanation

The correct answer is A: Add the vPC member ports to the vPC channel group.. The interfaces need to be added to the Portchannel. Configuring allowed VLANs on the vPC peer-link is optional.

Network

Question

Refer to the exhibit. Which action completes the vPC domain implementation?

Options

  • AAdd the vPC member ports to the vPC channel group.
  • BConfigure the system MAC on the vPC domain.
  • CInclude the VRF management on the vPC domain.
  • DAllow VLANs on the vPC peer link member interfaces.

Explanation

The interfaces need to be added to the Portchannel. Configuring allowed VLANs on the vPC peer-link is optional.

Topics

#vPC#Cisco Nexus#Network Redundancy#Data Center Networking

Community Discussion

No community discussion yet for this question.