CiscoCisco
350-601 · Question #294
350-601 Question #294: Real Exam Question with Answer & Explanation
The correct answer is A: Add the vPC member ports to the vPC channel group.. The interfaces need to be added to the Portchannel. Configuring allowed VLANs on the vPC peer-link is optional.
Network
Question
Refer to the exhibit. Which action completes the vPC domain implementation?
Options
- AAdd the vPC member ports to the vPC channel group.
- BConfigure the system MAC on the vPC domain.
- CInclude the VRF management on the vPC domain.
- DAllow VLANs on the vPC peer link member interfaces.
Explanation
The interfaces need to be added to the Portchannel. Configuring allowed VLANs on the vPC peer-link is optional.
Topics
#vPC#Cisco Nexus#Network Redundancy#Data Center Networking
Community Discussion
No community discussion yet for this question.