EC-Council
312-76 · Question #38
You are working as a Project Manager in your organization. You are nearing the final stages of project execution, and looking towards the final risk monitoring and controlling activities. For your…
The correct answer is B. Requested changes. See the full explanation below for the reasoning.
Question
You are working as a Project Manager in your organization. You are nearing the final stages of project execution, and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?
Options
- AQuantitative risk analysis
- BRequested changes
- CRisk audits
- DQualitative risk analysis
How the community answered
(17 responses)- A6% (1)
- B76% (13)
- C12% (2)
- D6% (1)
Community Discussion
No community discussion yet for this question.