nerdexam
EC-Council

312-76 · Question #33

A project plan includes the Work Breakdown Structure (WBS) and cost estimates. Which of the following are the parts of a project plan? Each correct answer represents a complete solution. Choose all…

The correct answer is A. Risk identification B. Project schedule C. Risk analysis D. Team members list. See the full explanation below for the reasoning.

Question

A project plan includes the Work Breakdown Structure (WBS) and cost estimates. Which of the following are the parts of a project plan? Each correct answer represents a complete solution. Choose all that apply.

Options

  • ARisk identification
  • BProject schedule
  • CRisk analysis
  • DTeam members list
  • ESecurity Threat

How the community answered

(51 responses)
  • A
    84% (43)
  • E
    16% (8)

Community Discussion

No community discussion yet for this question.

Full 312-76 Practice