nerdexam
EC-Council

312-76 · Question #28

Which of the following elements of BCP process includes the areas of plan implementation, plan testing, and ongoing plan maintenance, and also involves defining and documenting the continuity…

The correct answer is D. Business continuity plan development. See the full explanation below for the reasoning.

Question

Which of the following elements of BCP process includes the areas of plan implementation, plan testing, and ongoing plan maintenance, and also involves defining and documenting the continuity strategy?

Options

  • ABusiness impact assessment
  • BScope and plan initiation
  • CPlan approval and implementation
  • DBusiness continuity plan development

How the community answered

(47 responses)
  • A
    2% (1)
  • B
    9% (4)
  • C
    15% (7)
  • D
    74% (35)

Community Discussion

No community discussion yet for this question.

Full 312-76 Practice