You are the project manager for a construction project. The project involves casting of a column in a very narrow space. Because of the lack of space, casting is highly dangerous. High technical…
The correct answer is A. Transference. See the full explanation below for the reasoning.
Question
You are the project manager for a construction project. The project involves casting of a column in a very narrow space. Because of the lack of space, casting is highly dangerous. High technical skill will be required for casting that column. You decide to hire a local expert team for casting that column. Which of the following types of risk response are you following?
Options
- ATransference
- BMitigation
- CAvoidance
- DAcceptance
How the community answered
(20 responses)- A70% (14)
- B15% (3)
- C10% (2)
- D5% (1)