Which of the following is established during the Business Impact Analysis by the owner of a process in accepted business continuity planning methodology?

The correct answer is B. Recovery Time Objective. See the full explanation below for the reasoning.

Question

Which of the following is established during the Business Impact Analysis by the owner of a process in accepted business continuity planning methodology?

Options

  • ARecovery Consistency Objective
  • BRecovery Time Objective
  • CRecovery Point Objective
  • DRecovery Time Actual

How the community answered

(29 responses)
  • A
    14% (4)
  • B
    76% (22)
  • C
    7% (2)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full 312-76 Practice