Which of the following disaster recovery tests includes the operations that shut down at the primary site, and are shifted to the recovery site according to the disaster recovery plan?

The correct answer is C. Full-interruption test. See the full explanation below for the reasoning.

Question

Which of the following disaster recovery tests includes the operations that shut down at the primary site, and are shifted to the recovery site according to the disaster recovery plan?

Options

  • AParallel test
  • BSimulation test
  • CFull-interruption test
  • DStructured walk-through test

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    3% (1)
  • C
    83% (24)
  • D
    7% (2)

Community Discussion

No community discussion yet for this question.