You work as a project manager for TYU project. You are planning for risk mitigation. You need to identify the risks that will need a more in-depth analysis. Which of the following activities will…

The correct answer is D. Qualitative analysis. See the full explanation below for the reasoning.

Question

You work as a project manager for TYU project. You are planning for risk mitigation. You need to identify the risks that will need a more in-depth analysis. Which of the following activities will help you in this?

Options

  • AQuantitative analysis
  • BEstimate activity duration
  • CRisk identification
  • DQualitative analysis

How the community answered

(58 responses)
  • A
    3% (2)
  • B
    7% (4)
  • C
    10% (6)
  • D
    79% (46)