312-76 · Question #171
You work as a project manager for TYU project. You are planning for risk mitigation. You need to identify the risks that will need a more in-depth analysis. Which of the following activities will…
The correct answer is D. Qualitative analysis. See the full explanation below for the reasoning.
Question
You work as a project manager for TYU project. You are planning for risk mitigation. You need to identify the risks that will need a more in-depth analysis. Which of the following activities will help you in this?
Options
- AQuantitative analysis
- BEstimate activity duration
- CRisk identification
- DQualitative analysis
How the community answered
(58 responses)- A3% (2)
- B7% (4)
- C10% (6)
- D79% (46)