Which of the following processes involves taking measures to alter or improve the risk position of an asset throughout the company?
The correct answer is C. Risk reduction. See the full explanation below for the reasoning.
Question
Which of the following processes involves taking measures to alter or improve the risk position of an asset throughout the company?
Options
- ARisk transference
- BRisk avoidance
- CRisk reduction
- DRisk acceptance
How the community answered
(44 responses)- A11% (5)
- B7% (3)
- C80% (35)
- D2% (1)