312-38 · Question #96
Which of the following recovery plans includes specific strategies and actions to deal with specific variances to assumptions resulting in a particular security problem, emergency, or state of…
The correct answer is A. Contingency plan. A Contingency Plan is correct because it is specifically designed to address particular variances from expected assumptions - meaning it outlines predefined responses to specific "what if" scenarios, security problems, or emergencies before they occur. A Disaster Recovery Plan…
Question
Options
- AContingency plan
- BDisaster recovery plan
- CBusiness continuity plan
- DContinuity of Operations Plan
How the community answered
(15 responses)- A93% (14)
- B7% (1)
Explanation
A Contingency Plan is correct because it is specifically designed to address particular variances from expected assumptions - meaning it outlines predefined responses to specific "what if" scenarios, security problems, or emergencies before they occur.
A Disaster Recovery Plan (DRP) focuses on restoring IT systems and data after a major disruption, not on addressing specific assumption variances. A Business Continuity Plan (BCP) is broader, covering how an organization keeps all business functions operating during and after a disruption - it's the umbrella, not the targeted response. A Continuity of Operations Plan (COOP) is a government-focused framework for maintaining essential functions at an alternate site during emergencies, again broader in scope than targeted variance responses.
Memory tip: Think "contingency = condition" - a contingency plan is conditional ("if this specific assumption fails, then do this"), making it the most targeted and assumption-specific of the four.