3101 · Question #41
The main server has failed and several G650 gateways have reconnected to alternate servers. What mechanism controls G650 failover?
The correct answer is D. IPSI priority list administered on the ESS. Avaya AuraTM Communication Manager Survivability - Page 45
Troubleshooting and Diagnostics
Question
The main server has failed and several G650 gateways have reconnected to alternate servers. What mechanism controls G650 failover?
Options
- AH.248 Link Bounce timer
- BH.323 Link Bounce timer
- CIPSI priority list administered on theLSP
- DIPSI priority list administered on the ESS
How the community answered
(51 responses)- A6% (3)
- B2% (1)
- C10% (5)
- D82% (42)
Explanation
Avaya AuraTM Communication Manager Survivability - Page 45
Topics
#G650 gateway#IPSI priority list#ESS#failover mechanism