Refer to the exhibit. An engineer is configuring Inter-VSAN routing for two Cisco MDS switches. The FSPF cost between the switches is 500, and the Cisco MDS core virtualizes an IVR NAT domain as…

The correct answer is B. The MDS-Core simulates an IVR NAT, and increases the cost to 501. Option B is correct because when the Cisco MDS core virtualizes (simulates) an IVR NAT domain, it automatically increments the FSPF cost by 1 - from 500 to 501. This deliberate cost bump ensures that real fabric paths are preferred over simulated IVR paths when both exist…

Implementation

Question

Refer to the exhibit. An engineer is configuring Inter-VSAN routing for two Cisco MDS switches. The FSPF cost between the switches is 500, and the Cisco MDS core virtualizes an IVR NAT domain as shown. Which statement about the topology is correct?

Exhibit

300-625 question #55 exhibit

Options

  • AThe MDS-Core simulates an IVR NAT, and the FSPF cost is 500.
  • BThe MDS-Core simulates an IVR NAT, and increases the cost to 501.
  • CThe MDS-Core simulates an IVR NAT, and decreases the cost to 400.
  • DThe MDS-Core simulates an IVR NAT, and increases the cost to 600.

How the community answered

(20 responses)
  • A
    10% (2)
  • B
    70% (14)
  • C
    15% (3)
  • D
    5% (1)

Explanation

Option B is correct because when the Cisco MDS core virtualizes (simulates) an IVR NAT domain, it automatically increments the FSPF cost by 1 - from 500 to 501. This deliberate cost bump ensures that real fabric paths are preferred over simulated IVR paths when both exist, preventing suboptimal routing.

Why the distractors are wrong:

  • A is wrong because it claims the cost stays at 500 - it ignores the mandatory +1 increment that IVR simulation applies.
  • C is wrong because IVR simulation never decreases FSPF cost; it only adds to it (and 400 would be a 100-unit drop, which has no basis in IVR behavior).
  • D is wrong because the increment is only +1, not +100 - a cost of 600 would represent a massive, unsupported penalty.

Memory tip: Think of IVR NAT simulation as adding a "virtual hop tax" of exactly 1 - just enough to make the simulated path less preferred than a real path, but not so much that it becomes unusable. "Virtual = +1."