300-620 · Question #109

An engineer must perform a Cisco ACI fabric upgrade that minimizes the impact on user traffic and allows only permitted users to perform an upgrade. Which two configuration steps should be taken to…

The correct answer is D. Divide switches into two or more maintenance groups. E. Grant the fabric administrator role to a user who performs an upgrade. To minimize traffic impact during a Cisco ACI fabric upgrade, switches should be divided into maintenance groups for a rolling upgrade. To control who can perform the upgrade, users must be granted the fabric administrator role.

ACI Management and Operations

Question

An engineer must perform a Cisco ACI fabric upgrade that minimizes the impact on user traffic and allows only permitted users to perform an upgrade. Which two configuration steps should be taken to meet these requirements?

Options

  • ADivide Cisco APIC controllers into two or more maintenance groups.
  • BGrant tenant-ext-admin access to a user who performs an upgrade
  • CCombine all switches into an upgrade group.
  • DDivide switches into two or more maintenance groups.
  • EGrant the fabric administrator role to a user who performs an upgrade.

How the community answered

(40 responses)
  • A
    8% (3)
  • B
    15% (6)
  • C
    5% (2)
  • D
    73% (29)

Why each option

To minimize traffic impact during a Cisco ACI fabric upgrade, switches should be divided into maintenance groups for a rolling upgrade. To control who can perform the upgrade, users must be granted the fabric administrator role.

ADivide Cisco APIC controllers into two or more maintenance groups.

Dividing APIC controllers into maintenance groups is crucial for APIC availability during an upgrade but does not directly address minimizing impact on user traffic, which primarily flows through the data plane switches.

BGrant tenant-ext-admin access to a user who performs an upgrade

The tenant-ext-admin role is a tenant-level role and does not possess the necessary fabric-level privileges required to perform a Cisco ACI fabric upgrade.

CCombine all switches into an upgrade group.

Combining all switches into a single upgrade group would lead to all switches being upgraded simultaneously, causing significant disruption and maximum impact on user traffic, which violates the requirement to minimize impact.

DDivide switches into two or more maintenance groups.Correct

Dividing switches into two or more maintenance groups allows for a rolling upgrade process, ensuring that not all switches are taken offline simultaneously, which significantly minimizes the impact on user traffic.

EGrant the fabric administrator role to a user who performs an upgrade.Correct

The fabric administrator role provides the necessary permissions to manage and perform upgrades across the entire Cisco ACI fabric, satisfying the requirement that only permitted users can initiate the upgrade process.

Concept tested: Cisco ACI fabric upgrade best practices and RBAC

Source: https://www.cisco.com/c/en/us/td/docs/switches/datacenter/aci/apic/sw/3-x/upgrade/b_Cisco_APIC_and_Fabric_Upgrade_Guide/b_Cisco_APIC_and_Fabric_Upgrade_Guide_chapter_01.html

Topics

#fabric upgrade#maintenance groups#APIC upgrade#access control

Community Discussion

No community discussion yet for this question.