A company data center requires a new disaster recovery solution to host critical services. The solution can sustain several hours of data loss because the services are routinely backed up to an offsit

The correct answer is C. warm standby. Warm standby solutions maintain a secondary site that is partially active and pre-configured, ready to take over quickly but does not run all services fully active 24/7. This balances cost and availability by keeping resources ready without full continuous operation. It supports

Compute Design

Question

A company data center requires a new disaster recovery solution to host critical services. The solution can sustain several hours of data loss because the services are routinely backed up to an offsite location. Also, the disaster recovery solution must provide 24-hour availability. Due to the strict policy requirements, the company wants to retain complete control of when the failover process occurs. Which solution meets these requirements?

Options

  • Aactive/active
  • Bhot standby
  • Cwarm standby
  • Dcold standby

How the community answered

(22 responses)
  • A
    14% (3)
  • B
    5% (1)
  • C
    77% (17)
  • D
    5% (1)

Explanation

Warm standby solutions maintain a secondary site that is partially active and pre-configured, ready to take over quickly but does not run all services fully active 24/7. This balances cost and availability by keeping resources ready without full continuous operation. It supports manual initiation of failover, allowing the company to control precisely when the failover occurs, which aligns with the strict policy requirements. Warm standby can sustain several hours of data loss, fitting the scenario where backups allow some data recovery delay.

Topics

#disaster recovery#RPO/RTO#availability#warm standby