An engineer installs a B-Series server in a Cisco UCS chassis that contains a pair of UCS-IOM- 2208XP I/ O modules. The full bandwidth of the I/O module must be utilized. Which two elements should be

The correct answer is C. eight twinax cables from each I/O module to each fabric interconnect E. Cisco UCS VIC 1280. 2208 has 8 uplinks. VIC 1225 only works on C-Series UCS. M81KR has only 2x10G ports. VIC 1280 has 8x10G ports. card/ucs-vic-m82-8p/13785476

Compute Design

Question

An engineer installs a B-Series server in a Cisco UCS chassis that contains a pair of UCS-IOM- 2208XP I/ O modules. The full bandwidth of the I/O module must be utilized. Which two elements should be used in this environment? (Choose two.)

Options

  • Afour twinax cables from each I/O module to each fabric interconnect
  • BCisco UCS VIC 1225
  • Ceight twinax cables from each I/O module to each fabric interconnect
  • DCisco UCS M81KR
  • ECisco UCS VIC 1280

How the community answered

(37 responses)
  • A
    16% (6)
  • B
    5% (2)
  • C
    70% (26)
  • D
    8% (3)

Explanation

2208 has 8 uplinks. VIC 1225 only works on C-Series UCS. M81KR has only 2x10G ports. VIC 1280 has 8x10G ports. card/ucs-vic-m82-8p/13785476

Topics

#Cisco UCS#B-Series servers#I/O modules#VIC