An engineer is configuring an AP for a site survey. How should the transmit power be configured?

The correct answer is B. Set to one level below full power. During a site survey, the AP transmit power should be set to one level below full (maximum) power. This is because in actual deployment, APs are rarely run at absolute maximum power, and RF conditions such as co-channel interference often cause RRM or manual configuration to…

WLAN Design

Question

An engineer is configuring an AP for a site survey. How should the transmit power be configured?

Options

  • ASet to maximum power.
  • BSet to one level below full power.
  • CEnable DTPC.
  • DSet to one level above the lowest power level.

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    93% (26)
  • D
    4% (1)

Explanation

During a site survey, the AP transmit power should be set to one level below full (maximum) power. This is because in actual deployment, APs are rarely run at absolute maximum power, and RF conditions such as co-channel interference often cause RRM or manual configuration to reduce power slightly. Surveying at one level below max produces results that more accurately reflect the real post-deployment environment. Setting to maximum may give overly optimistic coverage maps, while DTPC (answer C) is a client-side feature, not an AP survey configuration.

Topics

#transmit power#survey AP configuration#TX power level#site survey