300-360 · Question #73
300-360 Question #73: Real Exam Question with Answer & Explanation
The correct answer is A: Determine the project scope, type of deployment, timeline, scale, budget, and users. The planning phase of a site survey focuses on gathering business and organizational context before any physical or technical work begins. Determining the project scope, deployment type, timeline, scale, budget, and user requirements (A) establishes the foundational constraints f
Question
Options
- ADetermine the project scope, type of deployment, timeline, scale, budget, and users
- BDetermine project stakeholders
- CDetermine customer training requirements
- DDetermine AP and controller placement
- EDetermine the customer applications that the network will support
- FDetermine radio spectrum and channel allocation
- GSchedule customer end user interviews
Explanation
The planning phase of a site survey focuses on gathering business and organizational context before any physical or technical work begins. Determining the project scope, deployment type, timeline, scale, budget, and user requirements (A) establishes the foundational constraints for all subsequent decisions. Identifying project stakeholders (B) ensures the right people are engaged and that decisions have proper approval paths. Determining the customer applications the network will support (E) directly informs design requirements such as required bandwidth, latency, and coverage. AP and controller placement (D) and radio spectrum/channel allocation (F) are outputs of the survey and design phase, not inputs to the planning phase. Customer end-user interviews (G) and training requirements (C) are post-deployment operational concerns, not site survey planning tasks.