A network has two Cisco WLCs and two Layer 3 gigabit Ethernet switches. The customer requires two gigabit connections from each Cisco WLC to each of the switches that have copper RJ-45 gigabit…
The correct answer is A. Four straight-through Ethernet cables C. Four copper SFPs must be added to the kit list. The requirement is 2 connections per WLC × 2 WLCs = 4 total gigabit links. Cisco WLCs use SFP (Small Form-factor Pluggable) slots for their uplink/distribution ports rather than built-in copper RJ-45 ports. Because the switches have copper RJ-45 gigabit ports, the WLC SFP slots…
Question
A network has two Cisco WLCs and two Layer 3 gigabit Ethernet switches. The customer requires two gigabit connections from each Cisco WLC to each of the switches that have copper RJ-45 gigabit ports. What two additional hardware are needed to connect the Cisco WLCs to the network? (Choose two.)
Options
- AFour straight-through Ethernet cables
- BLayer 3 switching module in each of the Cisco WLCs
- CFour copper SFPs must be added to the kit list
- DTwo console cables
- EFour rollover Ethernet cables
How the community answered
(55 responses)- A89% (49)
- B2% (1)
- D4% (2)
- E5% (3)
Explanation
The requirement is 2 connections per WLC × 2 WLCs = 4 total gigabit links. Cisco WLCs use SFP (Small Form-factor Pluggable) slots for their uplink/distribution ports rather than built-in copper RJ-45 ports. Because the switches have copper RJ-45 gigabit ports, the WLC SFP slots must be populated with copper 1000BASE-T SFPs (not fiber SFPs), requiring 4 copper SFPs total. Each copper SFP connects to the switch via a standard straight-through Cat5e/Cat6 Ethernet cable, so 4 straight-through cables are also needed. Console cables are for out-of-band management only, and Layer 3 switching modules in the WLC are not a requirement for physical uplink connectivity.