300-360 · Question #112
300-360 Question #112: Real Exam Question with Answer & Explanation
The correct answer is B: PoE capability. Hardware parameters during a pre-installation site survey focus on physical infrastructure readiness. PoE capability (B) confirms whether existing switches can power the access points. Switch port availability (E) ensures there are enough ports to connect all planned APs. Distanc
Question
Options
- Arouting protocol used
- BPoE capability
- Cswitch STP capability
- Ddistance of antenna to communications room
- Eswitch port availability
- Fdistance of access point to communications room
Explanation
Hardware parameters during a pre-installation site survey focus on physical infrastructure readiness. PoE capability (B) confirms whether existing switches can power the access points. Switch port availability (E) ensures there are enough ports to connect all planned APs. Distance of the access point to the communications room (F) is critical because Ethernet runs cannot exceed 100 meters; exceeding this requires intermediate switches or fiber. Routing protocol (A) and STP capability (C) are Layer 3/Layer 2 logical configurations, not hardware inspections. Distance of antenna to communications room (D) is a distractor, as the relevant distance is from the AP itself, not just the antenna.
Community Discussion
No community discussion yet for this question.