Which two information points should a pre-site survey questionnaire contain? (Choose two.)

The correct answer is B. hours during which the survey can be performed D. approximate square footage of facility. A pre-site survey questionnaire should capture logistical and physical scope information that is known before the survey, not design outputs that the survey itself will determine.

WLAN Design

Question

Which two information points should a pre-site survey questionnaire contain? (Choose two.)

Exhibit

300-360 question #103 exhibit

Options

  • Alist of clients used
  • Bhours during which the survey can be performed
  • Caccess point density required
  • Dapproximate square footage of facility
  • Etotal number of APs in use

How the community answered

(47 responses)
  • A
    2% (1)
  • B
    91% (43)
  • C
    2% (1)
  • E
    4% (2)

Why each option

A pre-site survey questionnaire should capture logistical and physical scope information that is known before the survey, not design outputs that the survey itself will determine.

Alist of clients used

A list of clients used is a detailed technical input relevant to device capability analysis but is not a standard logistical item collected in a pre-site survey questionnaire.

Bhours during which the survey can be performedCorrect

Hours during which the survey can be performed are a logistical constraint that must be collected before the site visit so the survey team can schedule access and plan the work appropriately.

Caccess point density required

Access point density is a design output determined by the survey results, not information that can be meaningfully known or provided before the survey is conducted.

Dapproximate square footage of facilityCorrect

Approximate square footage of the facility is fundamental pre-survey input that helps the engineer estimate survey duration, number of survey passes, and overall project scope before arriving on site.

Etotal number of APs in use

Total number of APs currently in use describes existing infrastructure and is assessed during the survey or site audit phase, not collected as a pre-survey questionnaire item.

Concept tested: Pre-site survey questionnaire essential input items

Source: https://www.cisco.com/c/en/us/td/docs/solutions/Enterprise/Mobility/WiFiLanDG/WiFiLanDG.html