Once a super metric is created, what is required in order for it to be calculated and available for use? (Choose the best answer.)

The correct answer is B. Assign it to one or more object types, then enable it in one or more policies. https://blogs.vmware.com/management/2017/04/creating-percentage-super-metric-vrealize-

Optimize vRealize Operations Manager

Question

Once a super metric is created, what is required in order for it to be calculated and available for use? (Choose the best answer.)

Options

  • AEnsure the Enable check box in the super metric creation pop-up window is selected
  • BAssign it to one or more object types, then enable it in one or more policies
  • CAssign it to one or more user groups so that members can use it
  • DAdd it to one or more custom groups and/or application definitions

How the community answered

(23 responses)
  • A
    13% (3)
  • B
    74% (17)
  • C
    9% (2)
  • D
    4% (1)

Explanation

https://blogs.vmware.com/management/2017/04/creating-percentage-super-metric-vrealize-

Topics

#super metrics#policy assignment#object types#metric enablement