A rebalance plan from the Rebalance Container action includes which three pieces of information? (Choose three.)

The correct answer is A. Destination cluster D. Reason for move E. Virtual machines to be moved. https://docs.vmware.com/en/vRealize-Operations- Manager/6.5/com.vmware.vcom.core.doc/GUID-92F9F9E0-2D6F-487F-90DE- C5940EE43494.html

Optimize vRealize Operations Manager

Question

A rebalance plan from the Rebalance Container action includes which three pieces of information? (Choose three.)

Options

  • ADestination cluster
  • BApplications impacted
  • CTime the virtual machine was last moved
  • DReason for move
  • EVirtual machines to be moved

How the community answered

(27 responses)
  • A
    78% (21)
  • B
    15% (4)
  • C
    7% (2)

Explanation

https://docs.vmware.com/en/vRealize-Operations- Manager/6.5/com.vmware.vcom.core.doc/GUID-92F9F9E0-2D6F-487F-90DE- C5940EE43494.html

Topics

#rebalance container#workload balancing#VM migration#rebalance plan details