2V0-21.23 · Question #78
2V0-21.23 Question #78: Real Exam Question with Answer & Explanation
The correct answer is B: Configure VMware a Site Recovery Manager and combine it with vSphere Replication.. https://blogs.vmware.com/virtualblocks/2017/11/29/vsr-technicaloverview/
Question
An administrator is tasked with looking into the disaster recovery (DR) options for a software- defined data center (SDDC). The following requirements must be met: - All virtual machines (VMs) must be protected to a secondary site. - The source VMs must remain online until the failover. - When failing over to the secondary site, application downtime is allowed. - The DR failover must be managed from the vSphere Client. - Costs must remain as low as possible. How can the administrator accomplish this task?
Options
- AConfigure VMware Cloud Disaster Recovery (VCDR) and combine it with array-based stor-age
- BConfigure VMware a Site Recovery Manager and combine it with vSphere Replication.
- CConfigure a subscribed content library on the secondary site.
- DConfigure VMware Site Recovery Manager and combine it with array-based storage replica-tion.
Explanation
https://blogs.vmware.com/virtualblocks/2017/11/29/vsr-technicaloverview/