The correct answer is A. A constraint. This is a constraint, as it defines a non-negotiable time limit imposed by the customer's budgeting timeline. It restricts the design phase's schedule and deliverables. In VMware conceptual modeling, timing constraints are explicitly captured as constraints rather than requiremen

Question

As part of an initial stakeholder meeting, one of the stakeholders has stated the following: The initial design must be completed within the next 3 months so that hardware can be ordered within the current budget cycle. How would the architect classify and record this statement?

Options

  • AA constraint
  • BA risk
  • CAn assumption
  • DA requirement

Explanation

This is a constraint, as it defines a non-negotiable time limit imposed by the customer's budgeting timeline. It restricts the design phase's schedule and deliverables. In VMware conceptual modeling, timing constraints are explicitly captured as constraints rather than requirements or

Community Discussion

No community discussion yet for this question.

Full 2V0-13.25 Practice