During a VMware Cloud Foundation (VCF) architectural design workshop, one of the stakeholders made the following comment: "The company has just used the remaining budget to purchase eight vSAN Ready…
The correct answer is D. Constraint. This statement expresses a financial limit - "Remaining budget" - constraining future expenditures on hardware. This is clearly a constraint, as it restricts the design options (e.g., can't procure new hardware). In the VMware Conceptual Model framework, constraints are factors…
Question
During a VMware Cloud Foundation (VCF) architectural design workshop, one of the stakeholders made the following comment:
"The company has just used the remaining budget to purchase eight vSAN Ready Nodes for this project." How would the architect classify this statement within the conceptual model document?
Options
- ARequirement
- BRisk
- CAssumption
- DConstraint
How the community answered
(65 responses)- A5% (3)
- B2% (1)
- C2% (1)
- D92% (60)
Explanation
This statement expresses a financial limit - "Remaining budget" - constraining future expenditures on hardware. This is clearly a constraint, as it restricts the design options (e.g., can't procure new hardware). In the VMware Conceptual Model framework, constraints are factors that limit design choices without introducing risk or goal definitions.