An architect is responsible for the design of a VMware Cloud Foundation (VCF) Fleet and the following risk has been identified: RISK001: There is a risk that frequent infrastructure design changes…

The correct answer is C. Develop a process to review and update DR plans between changes and schedule monthly end-. Establishing a formal process to review and update DR plans with each design change, along with scheduled end-to-end DR tests, ensures that DR strategies remain aligned with the evolving infrastructure and Service Level Objectives.

Section 2 – Design VMware Cloud Foundation Solutions

Question

An architect is responsible for the design of a VMware Cloud Foundation (VCF) Fleet and the following risk has been identified:

RISK001: There is a risk that frequent infrastructure design changes may break Disaster Recovery (DR) plans and Service Level Objectives. What should the architect suggest to mitigate this risk?

Options

  • AConfigure VM replication with recovery point objective of 5 minutes or less for all workloads from
  • BSetup monitoring & alerting against defined infrastructure service level objectives.
  • CDevelop a process to review and update DR plans between changes and schedule monthly end-
  • DLimit infrastructure design change frequency to a maximum of once a month.

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    10% (3)
  • C
    67% (20)
  • D
    20% (6)

Explanation

Establishing a formal process to review and update DR plans with each design change, along with scheduled end-to-end DR tests, ensures that DR strategies remain aligned with the evolving infrastructure and Service Level Objectives.

Topics

#disaster recovery#risk mitigation#DR planning#SLO management