Question

During the implementation phase of an Electronic Document Management System (EDMS) project, the Project Manager discovers that the storage system will not arrive by its targeted installation date. What is the next step?

Options

  • AProceed as normal because the project schedule will resolve itself
  • BChange the project Gantt chart to reflect the new expected date
  • CCreate a project change request and submit it to the project committee
  • DOrder a storage system from another vendor

Unlock 225-030 to see the answer