During the implementation phase of an Electronic Document Management System (EDMS) project, the Project Manager discovers that the storage system will not arrive by its targeted installation date…
The correct answer is C. Create a project change request and submit it to the project committee. See the full explanation below for the reasoning.
Question
During the implementation phase of an Electronic Document Management System (EDMS) project, the Project Manager discovers that the storage system will not arrive by its targeted installation date. What is the next step?
Options
- AProceed as normal because the project schedule will resolve itself
- BChange the project Gantt chart to reflect the new expected date
- CCreate a project change request and submit it to the project committee
- DOrder a storage system from another vendor
How the community answered
(27 responses)- A7% (2)
- B4% (1)
- C74% (20)
- D15% (4)