CompTIA
225-030 · Question #235
Which of the following would be considered a project?
The correct answer is C. The implementation of an enterprise content system. See the full explanation below for the reasoning.
Question
Which of the following would be considered a project?
Options
- AThe daily backup of scanned images
- BThe continual improvement of a business process
- CThe implementation of an enterprise content system
- DAdding a new user to the document management security database
How the community answered
(34 responses)- A3% (1)
- B12% (4)
- C79% (27)
- D6% (2)
Community Discussion