A member of the implementation team discovers that the software vendor is issuing a new version. Which one of the following should be done?

The correct answer is D. Notify the Project Manager. See the full explanation below for the reasoning.

Question

A member of the implementation team discovers that the software vendor is issuing a new version. Which one of the following should be done?

Options

  • AUpgrade after the project completion date
  • BResearch the new product to understand its features
  • CInform the business sponsors
  • DNotify the Project Manager

How the community answered

(50 responses)
  • A
    10% (5)
  • B
    2% (1)
  • C
    6% (3)
  • D
    82% (41)