220-1102 · Question #162
220-1102 Question #162: Real Exam Question with Answer & Explanation
The correct answer is A: Risk analysis. Before any significant change like a server deployment is approved, a risk analysis is essential to identify potential impacts, vulnerabilities, and mitigation strategies.
Question
An administrator has submitted a change request for an upcoming server deployment. Which of the following must be completed before the change can be approved?
Options
- ARisk analysis
- BSandbox testing
- CEnd user acceptance
- DLessons learned
Explanation
Before any significant change like a server deployment is approved, a risk analysis is essential to identify potential impacts, vulnerabilities, and mitigation strategies.
Common mistakes.
- B. Sandbox testing, while valuable, is a form of testing that occurs after design and often before final production deployment, but the approval process itself requires an initial risk assessment to even decide if testing is warranted.
- C. End-user acceptance testing typically occurs later in the deployment cycle, after the server is built and potentially tested, to ensure it meets user requirements, not as a prerequisite for initial change approval.
- D. "Lessons learned" are gathered after a change or project is completed and reviewed, not before a change request is approved.
Concept tested. Change management process, risk assessment
Reference. learn.microsoft.com/en-us/azure/cloud-adoption-framework/manage/considerations/change-management
Topics
Community Discussion
No community discussion yet for this question.