The correct answer is A: Gateway utilization. The Gateway Utilization report shows the percentage of gateway channel capacity consumed over time, which is the key metric for determining whether an additional gateway is required.
Question
Which Cisco Unified Communications Manager device report provides key information to determine if an additional gateway is needed?
Options
- AGateway utilization
- BGateway summary
- CGateway detail
- DGateway and line group utilization
Explanation
The Gateway Utilization report shows the percentage of gateway channel capacity consumed over time, which is the key metric for determining whether an additional gateway is required.
Common mistakes.
- B. Gateway Summary provides a high-level overview of call counts and durations per gateway but does not express utilization as a percentage of total capacity.
- C. Gateway Detail lists individual call records passing through a gateway, which is useful for troubleshooting specific calls but does not indicate overall capacity utilization.
- D. Gateway and Line Group Utilization focuses on trunk groups and line group capacity rather than providing the gateway-level utilization percentage needed for gateway capacity planning.
Concept tested. Using Gateway Utilization report for capacity planning