nerdexam
Cisco

200-401 · Question #1

Drag and Drop Question Answer:

The correct answer is Mount the switch on the DIN rail; Wire the switch to the DC power supply; Wire the switch ground to common ground; Perform Switch configuration; Connect Patch cords. Switch Installation & Commissioning - Step Order Explained Overview This sequence follows the universal principle of physical → electrical → logical → network when commissioning industrial/managed switches mounted in a panel or enclosure. --- Step-by-Step Breakdown 1. Mount the s

Install and Maintain Industrial Network Components

Question

Drag and Drop Question Answer:

Exhibit

200-401 question #1 exhibit

Answer Area

Drag items

Wire the switch to the DC power supplyWire the DC power supplyMount the switch on the DIN railConnect Patch cordsWire the switch ground to common groundPerform Switch configuration

Correct arrangement

  • Mount the switch on the DIN rail
  • Wire the switch to the DC power supply
  • Wire the switch ground to common ground
  • Perform Switch configuration
  • Connect Patch cords

Explanation

Switch Installation & Commissioning - Step Order Explained

Overview

This sequence follows the universal principle of physical → electrical → logical → network when commissioning industrial/managed switches mounted in a panel or enclosure.


Step-by-Step Breakdown

1. Mount the switch on the DIN rail

Why first: Physical installation is always the prerequisite for everything else. You cannot safely wire or configure a device that isn't secured. DIN rail mounting also establishes the switch's final position, which determines cable routing and reach.

2. Wire the switch to the DC power supply

Why second: Once physically secured, you make the DC power input connections (typically +V and 0V/negative terminals). Power wiring comes before grounding because you're connecting the supply conductors first - the next step then ties the chassis to a safety reference.

3. Wire the switch ground to common ground

Why third: The chassis/earth ground bond is completed after the power conductors are landed. This ensures the switch has a proper safety ground before any configuration or live traffic occurs. Grounding before power-on is a safety and EMC requirement.

Common misconception: Some assume ground should be wired before the DC supply connections. In practice, the order of steps 2 and 3 matters less than ensuring both are done before powering on - but this sequence reflects standard wiring documentation conventions.

4. Perform Switch configuration

Why fourth: Configuration (VLANs, port settings, management IP, STP, etc.) is done before connecting network cables. This prevents the switch from participating in the live network in an unconfigured state, which can cause broadcast storms, spanning tree issues, or security gaps.

5. Connect Patch cords

Why last: Patch cords are connected only after the switch is powered, grounded, and fully configured. This is the "go live" step - connecting cables to a pre-configured switch ensures the network behaves predictably from the first packet.


The Distractor Item

"Wire the DC power supply" (not in the correct sequence) refers to wiring the power supply unit itself - a prerequisite task assumed to be already complete before this procedure begins. It is a deliberate distractor testing whether you conflate wiring the supply with wiring the switch to the supply.


Summary Rule

Mount → Power → Ground → Configure → Connect

Never connect patch cords to an unconfigured switch, and never skip grounding before power-on.

Topics

#drag and drop#unspecified

Community Discussion

No community discussion yet for this question.

Full 200-401 Practice