Identify the three true statements about the timing of DRM integrations.
The correct answer is C. Property queries may be run any time on any version. D. DRM integrations may be scheduled or run on demand. E. Once a version has been finalized, only data Managers may run exports. See the full explanation below for the reasoning.
Question
Identify the three true statements about the timing of DRM integrations.
Options
- AExports may be run any time on any version.
- BImports may be run any time on any version.
- CProperty queries may be run any time on any version.
- DDRM integrations may be scheduled or run on demand.
- EOnce a version has been finalized, only data Managers may run exports.
How the community answered
(22 responses)- A9% (2)
- B14% (3)
- C77% (17)
Community Discussion