nerdexam
Oracle

1Z0-588 · Question #13

Which three statements are true about the stakeholders in a DRM implementation?

The correct answer is A. Business users are initially brought into the project during the testing process. B. Source and target systems administrators have minimal involvement during the DRM C. The DRM administrator use both prebuilt and custom property definitions and property. See the full explanation below for the reasoning.

Question

Which three statements are true about the stakeholders in a DRM implementation?

Options

  • ABusiness users are initially brought into the project during the testing process.
  • BSource and target systems administrators have minimal involvement during the DRM
  • CThe DRM administrator use both prebuilt and custom property definitions and property
  • DThe DRM administrator creates validations dictated by requirements and design.
  • EA data governance team defines overall standards for the DRM implementation.

How the community answered

(23 responses)
  • A
    78% (18)
  • D
    13% (3)
  • E
    9% (2)

Community Discussion

No community discussion yet for this question.

Full 1Z0-588 Practice