When Work Orders or Rate Schedules are completed, which four actions does the system perform?

The correct answer is A. Updates the Item Location File B. Updates unaccounted units in the Work Order Master D. Updates the Bill of Material E. Updates the Production Cost Table. See the full explanation below for the reasoning.

Question

When Work Orders or Rate Schedules are completed, which four actions does the system perform?

Options

  • AUpdates the Item Location File
  • BUpdates unaccounted units in the Work Order Master
  • CWrites a record In the Item Ledger File
  • DUpdates the Bill of Material
  • EUpdates the Production Cost Table

How the community answered

(31 responses)
  • A
    74% (23)
  • C
    26% (8)