When changing the Bill of Material through an Engineering Change Order, which three statements are TRUE?

The correct answer is A. Updates the bills of material for the items on the ECO C. Validates the ECO for full approval before accepting the requested changes E. Updates the parent or component revision level. See the full explanation below for the reasoning.

Question

When changing the Bill of Material through an Engineering Change Order, which three statements are TRUE?

Options

  • AUpdates the bills of material for the items on the ECO
  • BUpdates the Work Order parts list related to the parent item
  • CValidates the ECO for full approval before accepting the requested changes
  • DDeletes Invalid records from Bill of Material
  • EUpdates the parent or component revision level

How the community answered

(42 responses)
  • A
    83% (35)
  • B
    12% (5)
  • D
    5% (2)