nerdexam
Oracle

1Z0-565 · Question #58

The customer requires that each item be tot controlled upon Work Order completion. The lot number will be system generated using Next Numbers and the system will also duplicate lots across its…

The correct answer is D. System constants and Item Branch/Plant Lot Process Type. See the full explanation below for the reasoning.

Question

The customer requires that each item be tot controlled upon Work Order completion. The lot number will be system generated using Next Numbers and the system will also duplicate lots across its various branches, what set up is required?

Options

  • ABranch/Plant Constants and Location Control
  • BManufacturing Constants and Item Branch/Plant Lot Process Type
  • CItem Master Lot Process Type and Item Branch/Plant Lot Process Type
  • DSystem constants and Item Branch/Plant Lot Process Type
  • EBranch/Plant Constants and Item Branch/Plant Serial Number

How the community answered

(27 responses)
  • A
    4% (1)
  • C
    7% (2)
  • D
    85% (23)
  • E
    4% (1)

Community Discussion

No community discussion yet for this question.