nerdexam
Oracle

1Z0-565 · Question #36

The customer wants to soft commit material to a Work Order when its parts list is attached and hard commit it when the stop paperwork is printed. Where is this set up?

The correct answer is D. Commitment Method. See the full explanation below for the reasoning.

Question

The customer wants to soft commit material to a Work Order when its parts list is attached and hard commit it when the stop paperwork is printed. Where is this set up?

Options

  • ABranch/Plant Constants
  • BManufacturing Constants
  • CItem Branch/Plant
  • DCommitment Method

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    10% (3)
  • D
    81% (25)

Community Discussion

No community discussion yet for this question.

Full 1Z0-565 Practice