1Z0-565 · Question #30

Material Requirement Planning will ______________.

The correct answer is D. Use only single-level planning to focus on the end item. See the full explanation below for the reasoning.

Question

Material Requirement Planning will ______________.

Options

  • ADetermine gross demand, subtract what Is on hand, and calculate net requirements
  • BUse information from the Bill of Material and inventor/ records to calculate the time-materials
  • CNot review or change the messages once they are generated
  • DUse only single-level planning to focus on the end item
  • EDevelop messages only for the purchase of end item

How the community answered

(21 responses)
  • B
    14% (3)
  • C
    5% (1)
  • D
    76% (16)
  • E
    5% (1)

Community Discussion

No community discussion yet for this question.