Oracle
1Z0-565 · Question #30
Material Requirement Planning will ______________.
The correct answer is D. Use only single-level planning to focus on the end item. See the full explanation below for the reasoning.
Question
Material Requirement Planning will ______________.
Options
- ADetermine gross demand, subtract what Is on hand, and calculate net requirements
- BUse information from the Bill of Material and inventor/ records to calculate the time-materials
- CNot review or change the messages once they are generated
- DUse only single-level planning to focus on the end item
- EDevelop messages only for the purchase of end item
How the community answered
(21 responses)- B14% (3)
- C5% (1)
- D76% (16)
- E5% (1)
Community Discussion
No community discussion yet for this question.