Oracle
1Z0-565 · Question #13
The project planning phase, which begins after the customer accepts the quote, consists of which three of these options?
The correct answer is A. Refine the project scope D. Actual costing E. Requirement plan. See the full explanation below for the reasoning.
Question
The project planning phase, which begins after the customer accepts the quote, consists of which three of these options?
Options
- ARefine the project scope
- BProject schedule
- CComplete the scheduled project tasks
- DActual costing
- ERequirement plan
How the community answered
(25 responses)- A76% (19)
- B16% (4)
- C8% (2)
Community Discussion
No community discussion yet for this question.