1Z0-498 · Question #79

In one of your implementations, you are required to synchronize the Fusion Project Information with Microsoft Project. During synchronization, you realize that the default settings are configured so…

The correct answer is A. task structure B. resources C. task attributes D. actual quantities and costs. See the full explanation below for the reasoning.

Question

In one of your implementations, you are required to synchronize the Fusion Project Information with Microsoft Project. During synchronization, you realize that the default settings are configured so that the project attributes are transferred. Identify four attributes that are imported into Microsoft Project.

Options

  • Atask structure
  • Bresources
  • Ctask attributes
  • Dactual quantities and costs
  • Escheduling and progress

How the community answered

(27 responses)
  • A
    85% (23)
  • E
    15% (4)

Community Discussion

No community discussion yet for this question.