Oracle
1Z0-498 · Question #79
In one of your implementations, you are required to synchronize the Fusion Project Information with Microsoft Project. During synchronization, you realize that the default settings are configured so…
The correct answer is A. task structure B. resources C. task attributes D. actual quantities and costs. See the full explanation below for the reasoning.
Question
In one of your implementations, you are required to synchronize the Fusion Project Information with Microsoft Project. During synchronization, you realize that the default settings are configured so that the project attributes are transferred. Identify four attributes that are imported into Microsoft Project.
Options
- Atask structure
- Bresources
- Ctask attributes
- Dactual quantities and costs
- Escheduling and progress
How the community answered
(27 responses)- A85% (23)
- E15% (4)
Community Discussion
No community discussion yet for this question.