nerdexam
Oracle

1Z0-498 · Question #38

When implementing Project Performance Reporting, the client has provided the following scenario: 1. Every time the project cost is greater than or equal to a threshold, then the project should be…

The correct answer is B. single threshold level value. See the full explanation below for the reasoning.

Question

When implementing Project Performance Reporting, the client has provided the following scenario: 1. Every time the project cost is greater than or equal to a threshold, then the project should be shown as critical. 2. As long as the project cost is less than the threshold, the project should be shown as on-track. Which Threshold Level Rule is the ideal candidate for this kind of KPI definition?

Options

  • Amultiple threshold levels
  • Bsingle threshold level value
  • Csingle threshold level range
  • Dmultiple threshold level value

How the community answered

(34 responses)
  • A
    6% (2)
  • B
    71% (24)
  • C
    15% (5)
  • D
    9% (3)

Community Discussion

No community discussion yet for this question.

Full 1Z0-498 Practice