nerdexam
Oracle

1Z0-498 · Question #72

Choose the correct statement related to the project start and end dates.

The correct answer is B. If the task dates roll up the task hierarchy automatically, then the project dates cannot be edited. See the full explanation below for the reasoning.

Question

Choose the correct statement related to the project start and end dates.

Options

  • AIf the task dates roll up the task hierarchy automatically, then the project dates can be edited.
  • BIf the task dates roll up the task hierarchy automatically, then the project dates cannot be edited.
  • CIn an auto roll up of task dates, the project start date does not coincide with the earliest task.
  • DIn an auto roll up of task dates, the project start date does not coincide with the latest task finish

How the community answered

(44 responses)
  • A
    5% (2)
  • B
    82% (36)
  • C
    5% (2)
  • D
    9% (4)

Community Discussion

No community discussion yet for this question.

Full 1Z0-498 Practice