Oracle
1Z0-498 · Question #59
Identify four predefined "Resource Classes" to spread curves can be assigned.
The correct answer is A. Labor C. Equipment D. Material Items E. Financial Resource. See the full explanation below for the reasoning.
Question
Identify four predefined "Resource Classes" to spread curves can be assigned.
Options
- ALabor
- BUsage
- CEquipment
- DMaterial Items
- EFinancial Resource
How the community answered
(35 responses)- A74% (26)
- B26% (9)
Community Discussion
No community discussion yet for this question.