Select three things the Major Axis on the Project Plan Gantt Chart timescale show when the minor axis is set to Months.
The correct answer is A. Years B. Half Years D. Quarters. See the full explanation below for the reasoning.
Question
Select three things the Major Axis on the Project Plan Gantt Chart timescale show when the minor axis is set to Months.
Options
- AYears
- BHalf Years
- CWeeks
- DQuarters
- EDays
How the community answered
(32 responses)- A84% (27)
- C9% (3)
- E6% (2)